Mumbai-Ahmedabad Bullet Train: NHSRCL installs 206,000 noise barriers, advances key construction milestones | File Photo

Mumbai: The Mumbai-Ahmedabad Bullet Train Project has achieved a significant milestone with the installation of 206,000 noise barriers along both sides of the 103 km. According to National High Speed Rail Corporation, for every 1 km stretch, 2,000 noise barriers have been strategically placed on each side of the viaduct.

“The noise barriers are designed to mitigate sound generated by the train and civil structures during operations. These barriers reflect and distribute aerodynamic noise produced by the train as well as the sound generated by the wheels running along the tracks. Each barrier measures 2 metres in height and 1 metre in width, with a weight of approximately 830-840 kg. In residential and urban areas, taller noise barriers of 3 metres have been installed. These include an additional 1- metre translucent polycarbonate panel above the 2- metre concrete barrier to ensure passengers enjoy unobstructed views” said an official of National High Speed Rail Corporation (NHSRCL).

“To support the production of these barriers, six dedicated factories have been established. Three factories are located in Ahmedabad, with one each in Surat, Vadodara, and Anand” he said.

The Mumbai-Ahmedabad Bullet Train Project has also made significant progress in key construction works. Over 243 km of viaduct construction has been completed, along with 352 km of pier work and 362 km of pier foundation work. Bridges have been constructed across 13 rivers, and multiple railway lines and highways have been crossed through five steel bridges and two PSC bridges.

“Track construction in Gujarat is progressing rapidly, with RC (Reinforced Concrete) Track Bed construction underway in Anand, Vadodara, Surat, and Navsari districts. 71 track km of RC track bed construction has been completed, and welding of rails has commenced on the viaduct” said an official.

In Maharashtra, the first concrete base-slab for the Mumbai Bullet Train Station has been successfully cast at a depth of 32 metres, equivalent to a 10-storey building. Work on the 21 km tunnel between Bandra-Kurla Complex (BKC) and Shilphata is underway, with an Intermediate Tunnel (ADIT) of 394 metres completed to facilitate main tunnel construction.

According to NHSRCL, construction of seven mountain tunnels using the New Austrian Tunnelling Method (NATM) is progressing in Palghar district. The only mountain tunnel in Gujarat has already been successfully completed.

The 12 stations along the corridor, designed with thematic elements and energy-efficient features, are under rapid construction. These user-friendly and energy-positive stations are designed to provide a world-class passenger experience while prioritizing sustainability.

“The Mumbai-Ahmedabad Bullet Train Project is not only transforming connectivity but also creating significant social and economic benefits, including the generation of thousands of jobs, the development of local industries, and improvements in regional infrastructure. It will also help in reducing travel time, enhancing mobility, and fostering regional development, the project is set to drive economic growth and elevate the quality of life across Gujarat and Maharashtra.”- Vivek Kumar Gupta, Managing Director, NHSRCL

“The noise barriers are designed to mitigate sound generated by the train and civil structures during operations. These barriers reflect and distribute aerodynamic noise produced by the train as well as the sound generated by the wheels running along the tracks. Each barrier measures 2 metres in height and 1 metre in width, with a weight of approximately 830-840 kg. In residential and urban areas, taller noise barriers of 3 metres have been installed. These include an additional 1- metre translucent polycarbonate panel above the 2- metre concrete barrier to ensure passengers enjoy unobstructed views” said an official of National High Speed Rail Corporation (NHSRCL).

“To support the production of these barriers, six dedicated factories have been established. Three factories are located in Ahmedabad, with one each in Surat, Vadodara, and Anand” he said.

The Mumbai-Ahmedabad Bullet Train Project has also made significant progress in key construction works. Over 243 km of viaduct construction has been completed, along with 352 km of pier work and 362 km of pier foundation work. Bridges have been constructed across 13 rivers, and multiple railway lines and highways have been crossed through five steel bridges and two PSC bridges.

“Track construction in Gujarat is progressing rapidly, with RC (Reinforced Concrete) Track Bed construction underway in Anand, Vadodara, Surat, and Navsari districts. 71 track km of RC track bed construction has been completed, and welding of rails has commenced on the viaduct” said an official.

In Maharashtra, the first concrete base-slab for the Mumbai Bullet Train Station has been successfully cast at a depth of 32 metres, equivalent to a 10-storey building. Work on the 21 km tunnel between Bandra-Kurla Complex (BKC) and Shilphata is underway, with an Intermediate Tunnel (ADIT) of 394 metres completed to facilitate main tunnel construction.

According to NHSRCL, construction of seven mountain tunnels using the New Austrian Tunnelling Method (NATM) is progressing in Palghar district. The only mountain tunnel in Gujarat has already been successfully completed.

The 12 stations along the corridor, designed with thematic elements and energy-efficient features, are under rapid construction. These user-friendly and energy-positive stations are designed to provide a world-class passenger experience while prioritizing sustainability.

“The Mumbai-Ahmedabad Bullet Train Project is not only transforming connectivity but also creating significant social and economic benefits, including the generation of thousands of jobs, the development of local industries, and improvements in regional infrastructure. It will also help in reducing travel time, enhancing mobility, and fostering regional development, the project is set to drive economic growth and elevate the quality of life across Gujarat and Maharashtra.”- Vivek Kumar Gupta, Managing Director, NHSRCL


Rahul Dev

Cricket Jounralist at Newsdesk

Leave a comment

Your email address will not be published. Required fields are marked *